Saint MBA550/ MBA550 Final Exam 2016

    Question

    Question 1.1.The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question. (Points : 5)

    successors

    predecessors

    successors and predecessors

    followers

    Question 2.2.Project management differs from management of more traditional day-to-day activities because: (Points : 5)

    it has limited time frame.

    it has an unlimited budget

    it is more expensive

    it involves more of the workforce

    Question 3.3.Which of the following could not be a linear programming problem constraint? (Points : 5)

    1A + 2B ? 3

    1A + 2B = 3

    1A + 2B > 3

    1A + 2B < 3

    Question 4.4.The theoretical limit on the number of constraints that can be handled by a linear programming problem is _____. (Points : 5)

    2

    3

    4

    unlimited

    Question 5.5.Which of the list of items below is not a component of a linear programming problem? (Points : 5)

    Constraints

    Objective function

    Decision variables

    Nonlinear residual

    Question 6.6.For most graphs, the constraint equations which intersect to form a solution point must be solved simultaneously: (Points : 5)

    because the solution coordinates from the graph cannot be visually read with high precision.

    in order to confirm the mathematically determined coordinates.

    in order to determine all of the optimal point solution.

    because the slope b and the y-intercept a are not always integers.

    Question 7.7.For the constraints given below, which point is in the feasible region of this minimization problem? 

    14x + 6y = 42 

    x + 3y = 6(Points : 5)

    x = 2; y = 5

    x = 1; y = 2

    x = 2; y = 1

    x = 2; y = 3

    Question 8.8.Binary variables are: (Points : 5)

    0 or 1 only.

    any integer value.

    any continuous value.

    any negative integer value.

    Question 9.9.In a 0-1 integer programming model, if the constraint x1 – x2 = 0, it means when project 2 is selected, project 1 ________ be selected.(Points : 5)

    must always

    can sometimes

    can never

    is already

    Question 10.10.For a linear programming problem, assume that a given resource has not been fully used. We can conclude that the shadow price associated with that constraint: (Points : 5)

    will have a positive value.

    will have a negative value.

    will have a value of zero.

    could have a positive, negative or a value of zero. (no sign restrictions).

    Question 11.11.Thecritical path is the ________ path through the n etwork. (Points : 5)

    longest

    shortest

    straightest

    most expensive

    Question 12.12.Elements of project planning include: (Points : 5)

    defining project objectives

    identifying activities to crash.

    calculating expected times and standard deviations

    conducting a “lessons learned” session

    Question 13.13.Mallory Furniture buys two products for resale: big shelves (B) and medium shelves (M). Each big shelf costs $500 and requires 100 cubic feet of storage space, and each medium shelf costs $300 and requires 90 cubic feet of storage space. The company has $75,000 to invest in shelves this week, and the warehouse has 18,000 cubic feet available for storage. Profit for each big shelf is $300 and for each medium shelf is $150. If the Mallory Furniture company decides to purchase 150 big shelves and no medium shelves, which of the two resources will be left over? (Points : 5)

    Investment money only

    Storage space only

    Investment money and storage space

    Neither investment money nor storage space

    Question 14.14. A linear programming model consists of: (Points : 5)

    decision variables

    an objective function

    constraints.

    all of the above

    Question 15.15.The term refers to testing how a problem solution reacts to changes in one or more of the model parameters. (Points : 5)

    Priority recognition

    Decision analysis

    Analysis of variance

    Sensitivity analysis

    Question 16.16.If a maximization linear programming problem consists of all less-than-or-equal-to constraints with all positive coefficients and the objective function consists of all positive objective function coefficients, then rounding down the linear programming optimal solution values of the decision variables will ________ result in a(n) ________ solution to the integer linear programming problem. (Points : 5)

    always; optimal

    always; non-optimal

    never; non-optimal

    sometimes; optimal

    Question 17.17.Decision variables: (Points : 5)

    measure the objective function

    measure how much or how many items to produce, purchase, hire, etc.

    always exist for each constraint

    measure the values of each constraint

    Question 18.18.Cully Turniture buys two products for resale: big shelves (B) and medium shelves (M). Each big shelf costs $500 and requires 100 cubic feet of storage space, and each medium shelf costs $300 and requires 90 cubic feet of storage space. The company has $75,000 to invest in shelves this week, and the warehouse has 18,000 cubic feet available for storage. Profit for each big shelf is $300 and for each medium shelf is $150. What is the storage space constraint? (Points : 5)

    90 B + 100 M = 18000

    90 B + 100 M = 18000

    100 B + 90 M = 18000

    500 B + 300 M = 18000

    Question 19.19.Multiple optimum solutions can occur when the objective function is _______ a constraint line. (Points : 5)

    unequal to

    equal to

    linear to

    parallel to

    Question 20.20.A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is ____. (Points : 5)

    7.0

    7.5

    8.0

    8.5