QUANTITATIVE ANALYSIS


    Click here to get an A+ paper at a Discount

    Competency 309.3.2: PERT/CPM Techniques ­ The graduate correctly applies PERT/CPM techniques
    to project management tasks.
    Objectives:
    309.3.2­01: Determine the critical path identified by a given PERT/CPM analysis.
    309.3.2­02: Utilize PERT analysis to determine the probability that a given project will meet a specified
    deadline for completion.
    309.3.2­03: Determine slack time for a given project activity.
    309.3.2­04: Determine scheduled start time for a given project activity.
    309.3.2­05: Determine scheduled completion time for a given project activity.
    309.3.2­06: Use time­cost trade­offs to appropriately crash a project network.

    Need a Professional Writer to Work on this Paper and Give you Original Paper? CLICK HERE TO GET THIS PAPER WRITTEN

    Introduction:
    This task requires candidates to prepare a program evaluation and review technique (PERT) chart and
    apply critical path method (CPM) techniques.
    Given:
    Company A is installing a Web­based customer­feedback system to meet customer needs for quick
    response when rolling out new products. A new product line is rolling out in 48 weeks and the customer­
    feedback system must be installed and running in time for the new product launch. Table 1.1 in the
    attached Excel spreadsheet “PERT/CPM Analysis Table” shows three estimates of the time it will take
    Company A to complete each of the project activities in the customer feedback system project (optimistic,
    probable, pessimistic).Company B is installing a similar feedback system to accompany a new product
    line and originally had the same time line as Company A.
    Company B just announced that its new product line is ahead of schedule and will be launched in 44
    weeks instead of the initially projected 48 weeks. Because the Web­based customer feedback system
    must be installed and running in time for the revised date of the product launch, something must be done
    to shorten implementation time required for the customer­feedback system project. Refer to Table 1.2 in
    the attached Excel spreadsheet “PERT/CPM Analysis Tables” that lists the expected time it will take to
    complete the activities if shortened as much as possible (crash time), the cost to complete the activity
    using normal resources (normal cost), and the cost of completing the activity on an accelerated basis
    (crash cost).

    Need a Professional Writer to Work on this Paper and Give you Original Paper? CLICK HERE TO GET THIS PAPER WRITTEN
    Task:
    A. Use the estimates for Company A in Table 1.1 to do each of the following:
    1. Determine the expected completion time for each of the nine project activities.
    a. Enter all your answers in Table 1.1, showing all of your work.
    2. Determine the variance for each project activity
    a. Entering all your answers in Table 1.1, showing all of your work.
    3. Prepare a PERT chart showing the network diagram with activity times and their expected
    durations.
    a. Identify the critical path in the PERT chart.
    Note: When the files opens, enter your name and student ID in the respective boxes so the

    task questions and problems will populate the worksheet. If the attached template does not
    open or is missing information, please contact Ecare for assistance with opening the file.
    Note: Any additional numbers included in the PERT chart will not be evaluated for
    correctness.
    Note: If you don’t have software to build a PERT chart, use text boxes with lines or arrows in a
    word processing program or a spreadsheet program.
    4. Determine each of the following, showing all of your work or reasoning:
    a. Expected duration of the entire project
    b. Slack for project Activity E
    c. Slack for project Activity C
    d. The earliest week project Activity F is scheduled to start
    e. The latest week project Activity G is scheduled to finish
    Note: Referencing a value in the PERT chart is not considered showing work. Please explain
    how the value was determined.
    5. Determine the probability of completing this project in time for the product launch in 48 weeks,
    showing all of your work.
    Note: You may want to use the complete cumulative normal table located at;

    http://homes.cs.washington.edu/~jrl/normal_cdf.pdf

    B. Use your results from part A1 and the data in Table 1.2 to determine the following:
    1. Maximum reduction in time
    a. Enter your answer for part B1 in Table 1.2, showing all your work.
    2. Crash cost per week
    a. Enter your answer for part B2 in Table 1.2, showing all your work.
    Note: For your responses to parts B1 and B2, assume that Company B has the same expected
    completion times for project activities as Company A.
    C. Identify the following by using your results from part B:
    1. Least costly activities to be crashed in order to complete the project within 44 weeks
    2. Number of weeks each of the activities identified in part C1 should be crashed to meet the
    deadline with the lowest possible increase in cost
    3. Total additional cost due to crashing of the activities identified in part C1
    D. When you use sources, include all in­text citations and references in APA format.

    Need a Professional Writer to Work on this Paper and Give you Original Paper? CLICK HERE TO GET THIS PAPER WRITTEN

    Note: To reduce unnecessary matches select ignore “small matches <20 words” and “bibliography.”
    Note: For definitions of terms commonly used in the rubric, see the attached Rubric Terms.
    Note: When using sources to support ideas and elements in a paper or project, the submission MUST
    include APA formatted in­text citations with a corresponding reference list for any direct quotes or
    paraphrasing. It is not necessary to list sources that were consulted if they have not been quoted or
    paraphrased in the text of the paper or project.
    Note: No more than a combined total of 30% of a submission can be directly quoted or closely
    paraphrased from sources, even if cited correctly. For tips on using APA style, please refer to the APA

    Handout web link included in the General Instructions section.

    File Attachments:
    1. PERT/CPM Tables. link opens in new window

    When the files opens, enter your name and student ID in the respective boxes so the task questions and problems will populate
    the worksheet.

    Web Links:
    1. Rubric Terms link opens in new window
    Evaluation Method

    Need a Professional Writer to Work on this Paper and Give you Original Paper? CLICK HERE TO GET THIS PAPER WRITTEN

    Click here to get an A+ paper at a Discount


    Order This Paper Now

                                                                                                                                      Order Now