Project and Risk Management

    Project and Risk Management

    Construction Planning
    NETWORK PROGRAMME FOR A BRIDGE PROJECT

    A concrete bridge is to be constructed for a motorway project and the following activities, durations and sequences of work have been established.

    An elevation and section of the proposed bridge is indicated in Fig 1.

    Activity Duration
    Site strip – complete bridge
    Pier A
    Excavate pier
    Blinding to pier
    Fix reinforcement & formwork to kicker
    Concrete pier foundation
    Reinforcement to abutment
    Fix formwork
    Concrete abutment
    Strip Formwork
    Deck slab (piers A to B)
    Fix precast concrete beams
    Fix formwork to deck
    Fabricate and fix reinforcement
    Concrete deck
    Strip formwork to deck
    Curing period prior to striking formwork 4 days

    3 days
    1 day
    3 days **
    1 day
    4 days
    5 days
    1 day
    2 days
    **repeat activities on deck between piers B and C

    1 day
    5 days **
    3 days
    1 day
    2 days
    7 days
    ** repeat activities on deck between piers B and C

    Resources to be allocated – Case 1

    The following resources of temporary works and plant are to be allocated for the bridge construction.

    One hydraulic excavator
    One pier shutter
    One set of formwork for the deck span between the piers.
    An assessment is required of the minimum construction period for the bridge project based on the above resources.

    Alternative considerations

    Make suggestions for reducing the contract period by means of increasing resources for the project.
    .

    NOTE:- Produce a network diagram for the project utilising activity-on –arrow or precedence methods.