material planning

    The forecasting department, traditionally reporting to the sale manager, has historically seen a forecast accuracy of about 60%, and this in turn causes problems for the following departments: 

    • Purchasing: What should we buy and how much? 
    • Production: What should we really build? 
    • Inventory management: We keep building the wrong thing. 

    The sales manager asked you to write her a memo, specifically addressing the following:

    • How could you suggest that your new system would achieve any better levels of forecast accuracy? 
    • Why is forecast accuracy itself not as important under traditional methods? 
    • Create a chart or timeline that includes all of the following: 
      • Which purchase orders have to be placed, and when 
      • When manufacturing needs to begin, to have products delivered to a customer 
      • Approximate dates for all of the following: 
        • When the product must be shipped to meet the customer’s due date 
        • When the application of the cover and packaging must take place to meet the customer’s due date 
        • When the manufacturing of the widget must begin and end 
        • When the raw material for the widget must be ordered 
        • When the plastic cover must be ordered 
        • When the cardboard box must be ordered 
      • Includes notes explain your timing calculation 
      • Assumes all of the following conditions: 
        • The factory has two departments: manufacturing and packaging 
        • Product X consists of 3 components 
        • a widget manufactured in the factory with a total manufacturing lead time of 1 week 
        • a plastic cover purchased from vendor A with a procurement lead time of 3 weeks 
        • a cardboard shipping box purchased from vendor B with a procurement lead time of 4 weeks 
        • The widget itself is made from steel (whose lead time from vendor C is 4 weeks). 
        • It takes 1 day for the cover to be applied to the product and for the product to be inserted in the box in the packaging department. 
        • The shipping time to this customer is in 3 weeks, and you do not want it to be late or early. 
        • Assume you received the customer order on 1/1/20XX. 
        • Ignore any holidays 
        • Assume a 5-day work week 
        • The customer requires the product to arrive at his location on 3/31/2011