Management

    Management

    Competency 309.3.2: PERT/CPM Techniques – The graduate correctly applies PERT/CPM
    techniques to project management tasks.

    Objectives:
    Determine the critical path identified by a given PERT/CPM analysis. 309.3.2-02:
    Utilize PERT analysis to determine the probability that a given project will meet a specified
    deadline for completion.
    Determine slack time for a given project activity.
    Determine scheduled start time for a given project activity. 309.3.2-05: Determine
    scheduled completion time for a given project activity. 309.3.2-06: Use time-cost trade-offs to
    appropriately crash a project network.
    Introduction:
    This task requires candidates to prepare a program evaluation and review technique (PERT) chart and
    apply critical path method (CPM) techniques.
    Given:
    Company A is installing a Web-based customer-feedback system to meet customer needs for quick response when rolling out new products. A new product line is rolling out in 34 weeks and the
    customer-feedback system must be installed and running in time for the new product launch.

    Table 1.1 in the attached spreadsheet “PERT/CPM Tables” shows three estimates of the time it will
    take Company A to complete each of the activities and project tasks in the customer feedback system
    project (optimistic, probable, pessimistic).

    Company B is installing a similar feedback system to accompany a new product line and originally
    had the same time line as Company A. Company B just announced that its new product line is ahead of
    schedule and will be launched in 30 weeks instead of the initially projected 34 weeks. Because the
    Web-based customer feedback system must be installed and running in time for the revised date of
    the product launch, something must be done to shorten implementation time required for the
    customer-feedback system project. Refer to Table 1.2 in the attached worksheet “PERT/CPM Tables”
    that lists the expected time it will take to complete the activities if shortened as much as
    possible (crash time), the cost to complete the activity using normal resources (normal cost), and
    the cost of completing the activity on an accelerated basis (crash cost).

    Task:
    A. Use the estimates for Company A in Table 1.1 to do each of the following:
    1. Determine the expected completion time for each of the ten project activities, entering all
    your answers in Table 1.1 and showing all your work.
    a. Determine the variance for each project activity to two decimal places, entering all your
    answers in Table 1.1 and showing all of your work.

    2. Prepare a PERT chart (network diagram) and identify the critical path for project
    completion, using your calculated values from part A.

    Note: Any additional numbers included in the PERT chart will not be evaluated for correctness.

    Note: If you don’t have software to build a PERT chart, use text boxes with lines or arrows in a
    word processing program or Excel.

    3. Determine each of the following, showing all of your work or reasoning:

    Note: Referencing a value in the PERT chart is not considered showing work. Please explain how the value was determined for each of the following.

    a. Expected duration of the entire project
    b. Slack for project task A
    c. Slack for project task H
    d. The week project task F is scheduled to start
    e. The week project task I is scheduled to finish

    4. Determine the probability of completing this project in time for the product launch in 34
    weeks, showing all your work.

    Note: You may want to use the complete cumulative normal table located at the back of the book or
    at http://homes.cs.washington.edu/~jrl/normal_cdf.pdf.

    B. Assume that Company B has the same expected completion times for project activities as Company
    A. Use your results from part A1 to calculate the following information, entering all answers in
    Table 1.2 and showing all of your work:
    1. Maximum reduction in time
    2. Crash cost per week

    C. Identify the following by using your results from part B:
    1. Activities to be crashed in order to complete the project within 30 weeks.

    Note: All pathways must be within the 30 week deadline.

    2. Number of weeks each of these activities should be crashed to meet the deadlinewith the lowest
    possible increase in cost.
    3. Additional crashing cost of the activities identified in part C1.

    D. When you use sources, include all in-text citations and references in APA format.

    Note: To reduce unnecessary matches select ignore “small matches <20 words” and “bibliography”.

    ORDER THIS ESSAY HERE NOW AND GET A DISCOUNT !!!

     

                                                                                                                                      Order Now