UnitVICourseProjectComplete.doc

    2

    Cost Estimation and Budgeting

    James B. Christa

    Columbia Southern University

    Cost Estimation and Budgeting

    5. Project Budget

    5.1 Project Resources

    In this project, resources are categorized as follows

    i. Human resources: These are the members of the project team

    ii. Financial resources: This is the money needed to facilitate the project activities

    iii. Material resources: This refers to the machines, software, and other equipment and tools needed to make the project successful

    iv. Time resources: This is the time needed to undertake the project

    Resource

    Description

    Cost

    Human Resources

    They will be paid salaries and allowances for the duration of the project

    $ 800,000

    Financial Resources

    This is the total cost of the project

    $ 10,000,000

    Material resources

    This is the cost of buying all equipment, devices, machines, and tools needed in the project

    $ 9,200,000

    Time Resources

    This is the time that will be invested into ensuring the project is delivered

    N/A

    5.2 Other Costs

    Items

    Cost

    Equipment

    Full set computer systems (system units and monitors)

    $ 5,000,000

    Networking devices and cables

    $ 1,000,000

    Software

    $ 50,000

    Overhead Costs

    $ 30,000

    Expediting Expenses

    $ 20,000

    5.3 Cost Estimates

    Estimates

    Amount

    Ballpark estimate

    $ 10,000,000

    Comparative estimates

    $ 6,000,000

    Feasibility estimate

    $ 9,000,000

    The comparative estimate was based on the current system that should be upgraded. The estimate is lower than what the current project will cost because it is based on past data. The ballpark estimate is based on the idea that current equipment is more expensive. The project will cost more than the current system. The feasibility estimate was reached after the actual budget was developed. It is a more realistic estimate.

    5.4 Time-Phased Budget

    Month

    Activity

    May

    June

    July

    August

    September

    October

    Total by activity

    Survey

    $10,000

    $10,000

    Design

    $10,000

    $5,000

    $15,000

    Purchases

    $8,000,000

    $1,200,000

    $9,200,000

    Installation

    $10,000

    $5,000

    $10,000

    $25,000

    Testing

    $5,000

    $5,000

    $10,000

    Monthly Budget

    $20,000

    $5,000

    $8,010,000

    $1,205,000

    $15,000

    $5,000

    Cumulative

    $20,000

    $25,000

    $,8,035,000

    $9,060,000

    $9,075,000

    $9,260,000

    $9,260,000